11 Apr Murchison Project Works

Murchison Project Works

Our projects division has been engaged by a mining equipment OEM to install the electrical system associated with the installation of a new section of the tailings conveyor, as well as modifications to the existing conveyer structure, for an Iron Ore mine in the Murchison region of WA. The preparatory works will require 7 technicians for 10 days followed by a 22 person team consisting of 2 supervisors, 2 leading hands and 18 technicians to complete the main works over a 6 week period. The team will be split across a day and night shift in order to minimise the impact to the operating mine. ICM will be responsible for all HV, LV and ELV electrical works, instrumentation works and communication works including all pre and post energisation testing, commissioning and reporting.